WSSC Maintenance Projects

From Aspen Hill, Maryland, USA
Jump to: navigation, search

Here we record major projects and initiatives of the WSSC in Aspen Hill, Maryland.

Timeline

2010

March, 2010

Contract BR/CR4059A05

Begins water and sewer main repairs in the Aspen Hill Park subdivision with repairs/replacement of 4-inch line in Margot Court.

Below is a "best guess" schedule. As of March 11, 2010, the contractor is installing temporary bypass piping (water) along Eloise, McCall, Pacific, Arctic and Arbutus avenues.

BR/CR4059A05
ID Task Name                                          Duration      Start       Finish
1 INSTALL WATER MAIN ON MARGOT COURT                    3 days    Mon 3/1/10   Wed 3/3/10
2 INSTALL SEWER AND LATERALS ON MARGOT COURT          10 days     Thu 3/4/10  Wed 3/17/10
3 SEWER INSTALLATION MARGOT STREET                      3 days   Thu 3/18/10  Mon 3/22/10
4 SEWER LATERALS MARGOT STREET                          4 days   Tue 3/23/10   Fri 3/26/10
5 INSTALL SEWER ADRIAN STREET                           3 days   Mon 3/29/10  Wed 3/31/10
6 INSTALL SEWER LATERALS ADRIAN STREET                  4 days    Thu 4/1/10   Tue 4/6/10
7 SEWER INSTALLATION McCALL STREET                      3 days    Wed 4/7/10    Fri 4/9/10
8 SEWER LATERALS McCALL STREET                          4 days   Mon 4/12/10  Thu 4/15/10
9 SEWER INSTALLATION ARTIC STREET                       3 days    Fri 4/16/10 Tue 4/20/10
10 SEWER LATERALS ARTIC STREET                           3 days  Wed 4/21/10    Fri 4/23/10
11 LAY TEMP. WATER BYPASS- BALTIC AVE/ ADRIAN ST.      20 days     Mon 3/8/10    Fri 4/2/10
12 SAW CUTTING VARIOUS LOCATIONS                       25 days     Mon 3/8/10    Fri 4/9/10